Section 3Â Â MRP Structure 1) If 100 units of Q are needed and 10 are already in stock, then the gross requirement is 100 and the net requirement is 90. 2) Gross material requirements do not take into account the amount of inventory on hand. 3) When safety stock is deemed absolutely necessary, the usual policy is to build it into (increase) the inventory requirement of the MRP logic. 4) Consider the following product structure. If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed? A) 3 B) 40 C) 70 D) 90 E) 110 5) It is week 1 and there are currently 20 As in stock. We need 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week, when and how large of an order should be placed to meet the requirement of 300 As? A) Week 1, 300 As B) Week 1, 40 As C) Week 5, 40 As D) Week 4, 40 As E) Week 4, 300 As 6) If safety stock is desired, it should be built into which portion of MRP? A) any B) none C) raw materials D) finished goods E) either C or D 7) A material requirements plan contains information with regard to all of the following EXCEPT: A) quantities and required delivery dates of all subassemblies. B) quantities and required delivery dates of final products. C) the capacity needed to provide the projected output rate. D) inventory on hand for each final product. E) inventory on hand for each subassembly. 8) Which of the following best describes a gross material requirements plan? A) a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started B) an intermediate range plan for the scheduling of families of products C) a chart illustrating whether capacity has been exceeded D) a table that corrects scheduled quantities for inventory on hand E) a schedule showing which products are to be manufactured and in what quantities 9) Which of the following statements regarding the gross material requirements plan is TRUE? A) It shows total demand for an item. B) It shows when an item must be ordered from a supplier or when production must be started. C) It combines a master production schedule with the time-phased schedule. D) It requires several inputs, including an accurate bill of material. E) All of the above are true. 10) An order for 110 units of Product M has been placed. There are currently 30 units of Product M on hand. Each M requires 4 units of Component N. There are 20 units of N on hand. What are the net requirements for N? A) 150 B) 170 C) 300 D) 320 E) 440